Presentation
by Traflgar Multiplex SJB Architects and Parsons
Brinkerhoff (ex PPK) to Community
20 November 2002
(This page is based on the PowerPoint
presentation done. The presentation was a very
large computer file and so may images have been
sumnmarised in text. A couple of the most
important images are available. Click on the small
image to see a larger representation
1. Homebush Bay
Union Carbide Site
Development
Multiplex
Trafalgar
SynmanJustinBialek Architects
ParsonsBrinkerhoff
2. Agenda
5.45 Introductions, purpose of the meeting
5.50 Way forward on consultation re site development
6.00 Multiplex experience and what they are about
6.10 SJB experience and what they are about
6.20 Current community experience with development at Rhodes
6.30 Ideas for the ‘Renewing Homebush Bay’ project
Starting point - Development Control Plan
Initial ideas generation - SJB Architects
Key directions - discussion - All
7.30 Agenda for the next meeting/date
7.40 close
3. Who are we?
Multiplex
SJB Architects
Community
4. Renewing Homebush Bay Project - Starting Points
Development Control Plan
5. Subject site

{Trafalgar/Multiplex are redeveloping the former
Union Carbide site: B}
6. Regional Environmental Plan
Permits
Land for residential development
Land for parks and open spaces
Land for mixed development
7. Development Control Plan
Requirements to:
Create a specific identity for Rhodes Peninsula
Create a street layout that maximises connections, is permeable and safe
Creates public spaces that supplements and connects to existing networks
Ensure ecological sustainability
Optimise public transport
Create a lively public domain
Provide a high quality built environment
Provide workplace and housing choice
8. Development Control Plan
Sets out controls for:
street layout and character (nominated by street)
public spaces and what they contain
pedestrian amenity and accessibility
cycle and public transport
parking
ensuring views are provided
landscaping
street furniture, lighting and public art
design at water’s edge
on site water management
9. Development Control Plan
Sets out controls for:
Built form - uses, setbacks, storeys, building bulk, diversity of housing, building materials
Noise controls, privacy, sunlight, ventilation, waste management
10. Layout
{showed map of SREP 29 area showing street layout, parks, open space}
11. Public Domain:
Along the foreshore
Land set aside at specific points
{showed map of some of the public open space, part on Northern tip of Orica site, some on Southern part of Trafalgar site}
12. Initial Ideas Generation - Multiplex Ideas Competition
{Extracts from SJB ideas book}
13. Initial Ideas Generation – Initial worries
Block sizes

14. Initial Ideas Generation – Initial worries
Vistas

15. Initial Ideas Generation – Initial worries
Street Definition

16. Masterplan {Development control Plan - Issues
Summary}

17. Suggestion
18. Is the Street Layout Better?
Primary Secondary and Tertiary Streets clearer?
19. Stabilisers and Connectors
{stabiliser buildings at Water and Ridge, connectors in between then}
20. What else is important?
Variety and Texture
{photo of newington from air and distance
Newington has little variety of scale and texture}
21. Example of variety and texture
{drawing of looking at buildings face on}
22. Conceptual outline of site with variety of types of buildings
{Conceptual - hard to explain in words, but see
the site suggestion}
23. Site suggestion
See traf_suggestion.jpg and compare it with the
DCP layout: traf_dcp.jpg (NB the suggestion
only relates to a part of the area covered by the
DCP. the area is approx that marked in red.)

24. Renewing Homebush Bay Project – Process
Start ideas generation – talk with community liaison group
Community newsletter
Open community session
Prepare Development Application
Submit to Planning NSW – early 2003
Open community session
Exhibition
Determination